The Municipality of Clarington continues to receive, process and issue building permits. Building inspections are also proceeding.
Permit applications can be submitted in any of the following ways:
To help stop the spread of COVID-19, residents can continue to access our services by phone, online or by booking an appointment. If necessary, the Municipality will make special arrangements to conduct a building inspection virtually.
You can fill out your building permit application online on our website. To help facilitate your application, view our list of requirements for building permits.
If you have questions, please call 905-623-3379 ext. 2312 or email BuildingPermits@clarington.net.
Every building permit requires at least one or more inspections. It is the responsibility of the owner, or a representative designated by the owner, to arrange these inspections.
See the inspections page for more information on booking an inspection.
Footings: Readiness to construct footings with formwork and reinforcing in place prior to placing concrete.
Backfill: Substantial completion of footings and foundations, including drainage and damproofing prior to commencement of backfilling.
Framing: Substantial completion of structural framing after heating and ventilation, mechanical, and plumbing rough-in with windows and roofing in place.
Insulation: Substantial completion of the insulation and vapour barriers prior to covering.
Air barrier: Substantial completion of the air barrier system prior to covering.
Garage ceiling/floor insulation: Substantial completion of the insulation and vapour barriers in ceiling of garage and any floor over unheated space, prior to covering.
Building occupancy: Completion of the construction and installation of components required to permit occupancy, as required by the Ontario Building Code.
Footings: Readiness to construct footings with formwork and reinforcing in place prior to placing concrete.
Backfill: Substantial completion of footings and foundations, including drainage and damproofing prior to commencement of backfilling.
Framing: Substantial completion of structural framing and ductwork and piping for heating and air conditioning systems if the building is within the scope of Part 9 Division B.
Framing: Substantial completion of structural framing for each storey and rough-in of heating, ventilation, air conditioning, and air contaminant extraction equipment for buildings other than Part 9 Division B.
Insulation: Substantial completion of the insulation and vapour barriers prior to covering.
Air barrier: Substantial completion of the air barrier system prior to covering.
Fire separations: Substantial completion of all required fire separations and closures.
Building occupancy: Completion of the construction and installation of components required to permit the issue of an occupancy permit under Sentence 1.3.3.1(2) or to permit occupancy under Sentence 1.3.3.2(1), if the building to be occupied is not fully completed.
Contact(s)
Stay connected with Clarington, find out about Council meetings, festivals, events, and recreational opportunities.
Experience the joy of playing outdoors at Clarington's parks and sports fields. With over 70 parks to choose from, it's easy to find something fun to do.
We offer camps for every child and every interest. Located throughout Clarington, our camps are age appropriate, affordable and most of all, fun.
Get all the information you need on fitness, aquatic and recreation programs, as well as swimming and skating schedules. We offer programs for all ages and abilities.